Assessing a planning application

We have made a simple guide to help step you through the process of submitting your proposal to Council for assessment.

How your application is assessed

Step 1.Submitting your application

After you have submitted your application and the applicable fee has been paid, the application is accepted and assigned to a Planning Officer, who is responsible for assessing the application.

Note you might be asked for further information if the mandatory documentation is/are not supplied. This can cause delays to your application, so it is highly recommended you use the Planning Checklist which outlines the relevant documentation needed to accept a planning application.

Find out more about submitting your planning permit application.

Step 2.Initial assessment

The planner assesses all the submitted documentation to ensure there is sufficient information to make a well-informed decision. The planner may request further information (RFI) within 28 days of receipt of the application.

The application is put “on hold” until this information is received. If the information is not received within the prescribed timeframe (90 days), the application lapses.

The applicant may request an extension of time to the RFI in writing before the due date.

Step 3.Referral authorities

In some cases, the application may be forwarded to other Council departments and external authorities, such as Lower Murray Water or VicRoads, for specialist or technical advice. External authorities have up to 28 days to reply to Council.

Step 4.Giving public notice

Some planning permit applications are required to give notice of the application i.e. have it “advertised”. This means the application will be advertised to all persons likely to be affected by the proposal, usually the adjoining owners and occupiers.

The form of advertising required may include:

  • Notifying owners/occupiers of adjoining properties by mail
  • Sign on the site
  • Advertisement in the local paper (The Guardian or the Sentinel)

The notice period is for 14 days and Council must consider all submissions (objections) received up until the time a decision is made, even if this takes longer than 14 days.

Council cannot make a decision on an application until the advertising and notice period is complete.

Find out more about advertised planning applications.

Step 5.Amendments to application

You may amend your application at any time during the process, however if you make an amendment after the notice period, the application may have to be re-advertised and an additional fee will be charged.  

Find out more about amending a planning application

Step 6.Decision

There are three types of decisions that can be made on a planning permit:

  1. If there are no objections to the application and the application is supported, Council issues the planning permit.
  2. If there is an objection to the application, the application will be heard at a Council meeting and Council will either:
    • Issue a Notice of Decision (NOD) to grant a planning permit or
    • Issue a Notice of Decision (NOD) to refuse to grant a planning permit
  3. If the application is not supported, the application will be heard at a Council meeting and Council will either:
    • Issue a Notice of Decision (NOD) to refuse a planning permit or
    • Issue a Notice of Decision (NOD) to grant a planning permit

Notice of Decisions are not planning permits.  A notice of decision indicates that council is proposing to grant or refuse a permit. A notice of decision means that there is a period of 28 days in which an objector or 60 days which an applicant can appeal council's decision to the Victorian Civil and Administrative Tribunal (VCAT).

Find out more about objecting to a planning permit

Step 7.Appeal to VCAT

You can appeal to VCAT to review a Council decision about a planning permit application.

Find out more about appealing a planning permit decision.

Timeframes

The approval time for applications differs depending on the complexity of your application. If we need to advertise your application, it may take up to two months for approval. This time frame may increase if;

  • we need to ask for more information
  • we receive submissions from notified parties

View planning applications

Council's online planning application register allows users to search and view current and past planning permit applications.

View planning permit applications