Tower Hill Stage 15

  • Project typeNew asset
  • Estimated completionMay 2025

Project status as at 30 December 2024

  • BudgetOn budget
  • ScheduleBehind schedule
  • ScopeAgreed scope
  • Project updateStage 15: Major construction works complete.
    Still to be completed: Electrical – Audit of electrical services, obtain statement of compliance, Title registration.

    Public Open Space (POS): Concept design, community consultation, detailed design completed.
    Still to be completed: Tender, Construction of POS

This project involves the development of Stage 15 of Tower Hill, creating 25 new housing blocks to support the growing residential needs of the community and enhance the area's liveability.

Any dates provide are subject to contract agreement, weather conditions and any other unforeseen delays.

Location

Tower Hill, Swan Hill 3585  View Map

Google Map